1. Right Answer: B
Explanation: Planning for implementation should begin well in advance of the actual implementation date. A formal implementation plan should be constructed in the design phase and revised as the development progresses.
2. Right Answer: D
Explanation: A key tenet of the Agile approach to software project management is team learning and the use of team learning to refine project management and software development processes as the project progresses. One of the best ways to achieve this is that, at the end of each iteration, the team considers and documents what worked well and what could have worked better, and identifies improvements to be implemented in subsequent iterations. CMM and Agile really sit at opposite poles. CMM places heavy emphasis on predefined formal processes and formal project management and software development deliverables. Agile projects, by contrast, rely on refinement of process as dictated by the particular needs of the project and team dynamics.Additionally, less importance is placed on formal paper- based deliverables, with the preference being effective informal communication within the team and with key outside contributors. Agile projects produce releasable software in short iterations, typically ranging from 4 to 8 weeks. This, in itself, instills considerable performance discipline within the team. This, combined with short daily meetings to agree on what the team is doing and the identification of any impediments, renders task-level tracking against a schedule redundant. Agile projects do make use of suitable development tools; however, tools are not seen as the primary means of achieving productivity. Team harmony, effective communications and collective ability to solve challenges are of greater importance.
3. Right Answer: A
Explanation: A separate environment or environments is normally necessary for testing to be efficient and effective, and to ensure the integrity of production code, it is important that the development and testing code base be separate. When defects are identified they can be fixed in the development environment, without interrupting testing, before being migrated in a controlled manner to the test environment. A separate test environment can also be used as the final staging area from which code is migrated to production. This enforces a separation between development and production code. The logistics of setting up and refreshing customized test data is easier if a separate environment is maintained. If developers and testers are sharing the same environment, they have to work effectively at separate times of the day. It is unlikely that this would provide optimum productivity. Use of a source code control tool is a good practice, but it does not properly mitigate the lack of an appropriate testing environment. Even low priority fixes run the risk of introducing unintended results when combined with the rest of the system code. To prevent this, regular regression testing covering all code changes should occur. A separate test environment makes the logistics of regression testing easier to manage.
4. Right Answer: D
Explanation: The purpose of sociability testing is to confirm that a new or modified system can operate in its target environment without adversely impacting existing systems.This should cover the platform that will perform primary application processing and interfaces with other systems, as well as changes to the desktop in a client- server or web development. Parallel testing is the process of feeding data into two systems-the modified system and an alternate system- and comparing the results. In this approach, the old and new systems operate concurrently for a period of time and perform the same processing functions. Pilot testing takes place first at one location and is then extended to other locations. The purpose is to see if the new system operates satisfactorily in one place before implementing it at other locations. Interface/integration testing is a hardware or software test that evaluates the connection of two or more components that pass information from one area to another. The objective is to take unit-tested modules and build an integrated structure.
5. Right Answer: C
Explanation: When an IS auditor observes such conditions, it is best to fully apprise the auditee and suggest that further problem resolutions be attempted. Recording it as a minor error and leaving it to the auditee's discretion would be inappropriate, and neglecting the error would indicate that the auditor has not taken steps to further probe the issue to its logical end.