1. Right Answer: B
Explanation: Integrated change control is responsible for evaluating a proposed change and determining its impact on all areas of the project: scope, time, cost, quality, human resources, communication, risk, and procurement.Incorrect Answers:A: Configuration management defines the management, control, and documentation of the features and functions of the project's product.C: Risk analysis is not responsible for reviewing the change aspects for the entire project.D: The project change control system defines the workflow and approval process for proposed changes to the project scope, time, cost, and contracts.
2. Right Answer: B,D
Explanation: The enterprise must consider risk that has not yet occurred and should develop scenarios around unlikely, obscure or non-historical events.Such scenarios can be developed by considering two things: Visibility Recognition For the fulfillment of this task enterprise must: Be in a position that it can observe anything going wrong Have the capability to recognize an observed event as something wrongIncorrect Answers:A, C: These are not the direct requirements for developing obscure risk scenarios, like curing risk events comes under process of risk management. Hence capability of curing risk event does not lay any impact on the process of development of risk scenarios.
3. Right Answer: D
Explanation: Reasonableness tests make certain assumptions about the information as the basis for more elaborate data validation tests.Incorrect Answers:A: The duplicate test does not identify duplicate transactions; rather it identifies and confirms the validity of duplicates.B: The control total test does not ensure that all transactions have been extracted, but only ensures that the data are complete.C: As compared to simplistic, the reasonableness test is a valid foundation for more elaborate data validation tests.
4. Right Answer: D
Explanation: The risk exposure for this event is found by multiplying the risk impact by the risk probability.Risk Exposure is a straightforward estimate that gives a numeric value to a risk, enabling different risks to be compared.Risk Exposure of any given risk = Probability of risk occurring x impact of risk event= 0.70 * 350,000= 245,000Incorrect Answers:A: $350,000 is the impact of the risk event.B: $500,000 is the project's budget.C: $850,000 is the project's budget and the risk's impact.
5. Right Answer: C
Explanation: This is a verbal change request, and verbal change requests are never implemented. They introduce risk and cannot be tracked in the project scope. Change requests are requests to expand or reduce the project scope, modify policies, processes, plans, or procedures, modify costs or budgets or revise schedules.These requests for a change can be direct or indirect, externally or internally initiated, and legally or contractually imposed or optional. A Project Manager needs to ensure that only formally documented requested changes are processed and only approved change requests are implemented.Incorrect Answers:A: Including the verbal change request circumvents the project's change control system.B: Directing the project team to include the change request if they have time is not a valid option. The project manager and the project team will have all of the project team already accounted for so there is no extra time for undocumented, unapproved change requests.D: You may want to report Jane to the project sponsor, but you are not obligated to include the verbal change request.
Leave a comment